From: Building Coordinator List [mailto:BUILDINGCOORDINATOR at LISTSERV.UH.EDU] On Behalf Of Vargas, Jacquie
Sent: Thursday, November 13, 2014 1:16 PM
To: BUILDINGCOORDINATOR at LISTSERV.UH.EDU
Subject: Winter 2014 Outage Update
For distribution and communication -
In order to provide consistent and reliable electrical service on campus and to avoid future failures of the campus electrical system, pre-investigative and repair maintenance efforts are needed.
Please be advised that the University's plan to perform a complete campus electrical shut-down has been cancelled during the winter break 2014 until further notice.
As a result, brief electrical disruptions will take place over the winter break. These are scheduled to occur between Dec. 26 and Dec. 30.
Building backup generators will be online during the electrical blips, which will occur as systems are transferred to generator power. Once the work is completed, blips will occur as the campus electrical feeders are realigned and balanced. Impacts will be to intermediate distribution frame (IDF) equipment, computers, lab research equipment and any instrument that is not on an uninterrupted power supply (UPS).
Please make all necessary arrangements to protect equipment during these power disruptions.
The intent is not to disrupt research or teaching efforts. However, if any department determines that the scheduled power blips will be problematic and unacceptable, they should reach out so that efforts can be made to accommodate their needs.
Principal Project Manager Shannon Jones is leading the electrical outage and can be contacted at 713-743-4469 or sejones3 at Central.UH.EDU<mailto:sejones3 at Central.UH.EDU>. If additional support is required as far as any experiments or ongoing research, contact Facilities Management Executive Director Herman Taitt at 713-743-6563 or taitt at uh.edu<mailto:taitt at uh.edu>.
For assistance during the electrical disruptions, contact the Facilities Service Center at 713-743-4948 or csc at central.uh.edu<mailto:csc at central.uh.edu>.
For a list of buildings impacted by the electrical disruptions, or power blips, refer to the list provided below.
Buildings Impacted by the Pre-Investigative and Maintenance Related Power Blips -
Bldg.#
Building Name
Friday, 12/26/14
5:30 am - 6:30 am
Tuesday, 12/30/14
5:30 pm - 6:30 pm
(3 -- 10 second 1)
(2 - 3 second 2)
(2 - 3 second 3)
106
TLCC
X
498
Bulk Fueling Diesel Tank Farm
X
X
499
CBB
X
501
Roy Cullen
X
502
Science Building 1
X
X
503
Tech I Annex
X
505
Optometry
X
X
505
Optometry, Animal Care
X
X
507
Wortham Theater
X
508
Tech II
X
509
MDA Library
X
510
Cougar Place Res.
X
515
Central Plant
X
516
E. Cullen
X
518
Calhoun Lofts
X
X
X
520
Moore's School of Music
X
X
X
522
CRWC
X
X
X
523
Science Engineering Annex
X
X
524
Student Service Ctr. I
X
527
EHRM 1
X
X
528
Melcher Hall
X
531
Hofheinz Pavilion
X
534
Heyne Bldg.
X
535
EHRM 2
X
X
536
Center for Public Broadcasting
X
X
537
Bates Law
X
539
Krost Hall
X
543
Architecture Building
X
544
Cemo Hall
X
545
SERC
X
547
PGH
X
549
Social Work
X
550
SR1
X
X
X
551
SR2
X
X
X
559
Oberholtzer Residence Hall
X
563
Cougar Village 1
X
564
Lamar Fleming
X
X
X
565
University Center North
X
567
University Center Satellite
X
X
X
572
General Services Storage Bldg
X
X
574
Alumni Center
X
576
Science Teaching Lab
X
X
X
578
Agnes Arnold Hall
X
579
Engineering 1
X
X
X
580
Engineering Lecture Hall
X
X
581
Engineering 2
X
X
X
584
Moody Towers & Kitchen
X
X
X
585
General Service Bldg.
X
X
X
586
Cameron Bldg.
X
587
Farish Hall
X
589
Fine Arts
X
590
Hilton Hotel North
X
590
Hilton Hotel South
X
X
X
593
Houston Science Ctr.
X
X
X
594
Engineering Resource Ctr.
X
X
596
Computing Center
X
X
X
598
Clinical Research Services
X
1 Buildings that will see 3-10 second power blip for emergency generator testing. All of the listed buildings generators will run for a 12 - 48 hour period.
2 Buildings that will see multiple 2-3 second power blips on the entire normal power to the facility while Cougar 1 is isolated.
3 Buildings that will see multiple 2-3 second power blips on the entire normal power to the facility while Cougar 1 is put back into service and campus electrical feeder are realigned for load balancing.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://Bug.EGR.UH.EDU/pipermail/engi-dist/attachments/20141113/abb5933c/attachment-0001.html
More information about the Engi-Dist
mailing list