Please see the attached updated electrical outage notification. Times have been extended.
Ken Perlowski
From: Rea, Jennifer D On Behalf Of Facilities Communications
Sent: Tuesday, June 14, 2016 11:14 AM
To: Facilities Communications; Perlowski, Ken; Tyler R. Powell; Hawkins, Terry T; Reed, Shannon; Wysong, Mackenzie; Benham, Mary; Johnson, Andrea L; Simons, Spencer; Emerson, Allen L; Gonzalez, Robert G; Bangerter, Stephen A; Herbert, Geoffrey; Banks, Torik; sanchez-vanessa at ARAMARK.COM; Reado-sybil at ARAMARK.COM; ROBINSON, FELIX; Riggins, Claudia J; Kirkland, Lannis; Rosengren, James; Aguanno, James V
Cc: Simmons, Barry E; Vargas, Jacquie
Subject: Review: PLANNED ELECTRICAL OUTAGE NOTIFICATION -- MULTIPLE BUILDINGS (18 JUNE 2016) - UPDATED TIMES
BC's for Multiple Buildings,
The times for the PLANNED ELECTRICAL OUTAGE for Saturday, June 18, 2016 have been extended.
It will now be 6:00am - 6:30pm. If there are any issues to this time adjustment, we need to know in the next 24 hours.
If this time adjustment is acceptable, a simple reply would be great. If we have no reply in the next 24 hours, we will assume that the time adjustment is confirmed for your building users.
Thanks in advance for your help with this project and outage notification.
:)
Jennifer
Jennifer D. Rea
713-743-0247 office
jdrea2 at central.uh.edu<mailto:jdrea2 at central.uh.edu>
From: Rea, Jennifer D On Behalf Of Facilities Communications
Sent: Wednesday, June 08, 2016 9:51 AM
To: Perlowski, Ken <krperlow at Central.UH.EDU<mailto:krperlow at Central.UH.EDU>>; 'Tyler R. Powell' <TPowell at tellepsen.com<mailto:TPowell at tellepsen.com>>; Hawkins, Terry T <tthawkin at Central.UH.EDU<mailto:tthawkin at Central.UH.EDU>>; Reed, Shannon <sreed2 at Central.UH.EDU<mailto:sreed2 at Central.UH.EDU>>; Wysong, Mackenzie <mwysong at Central.UH.EDU<mailto:mwysong at Central.UH.EDU>>; Benham, Mary <MBenham at Central.UH.EDU<mailto:MBenham at Central.UH.EDU>>; Johnson, Andrea L <aljohnso at Central.UH.EDU<mailto:aljohnso at Central.UH.EDU>>; Simons, Spencer <SSimons at Central.UH.EDU<mailto:SSimons at Central.UH.EDU>>; Emerson, Allen L <alemerso at Central.UH.EDU<mailto:alemerso at Central.UH.EDU>>; Gonzalez, Robert G <GRobert at Central.UH.edu<mailto:GRobert at Central.UH.edu>>; Bangerter, Stephen A <sbangert at Central.UH.EDU<mailto:sbangert at Central.UH.EDU>>; Herbert, Geoffrey <Herbert-Geoffrey at aramark.com<mailto:Herbert-Geoffrey at aramark.com>>; 'Banks, Torik' <Banks-Torik at aramark.com<mailto:Banks-Torik at aramark.com>>; 'sanchez-vanessa at ARAMARK.COM' <sanchez-vanessa at ARAMARK.COM<mailto:sanchez-vanessa at ARAMARK.COM>>; 'Reado-sybil at ARAMARK.COM' <Reado-sybil at ARAMARK.COM<mailto:Reado-sybil at ARAMARK.COM>>; ROBINSON, FELIX <frrobins at Central.UH.EDU<mailto:frrobins at Central.UH.EDU>>; Riggins, Claudia J <cjriggin at Central.UH.EDU<mailto:cjriggin at Central.UH.EDU>>; Kirkland, Lannis <kirkland at Central.UH.EDU<mailto:kirkland at Central.UH.EDU>>; Rosengren, James <jrosengr at Central.UH.EDU<mailto:jrosengr at Central.UH.EDU>>
Cc: Simmons, Barry E <besimmon at Central.UH.EDU<mailto:besimmon at Central.UH.EDU>>; Jacquie Vargas (jmvarga5 at Central.UH.EDU<mailto:jmvarga5 at Central.UH.EDU>) <jmvarga5 at Central.UH.EDU<mailto:jmvarga5 at Central.UH.EDU>>
Subject: Review: PLANNED ELECTRICAL OUTAGE NOTIFICATION -- MULTIPLE BUILDINGS (18 JUNE 2016)
BC's for Multiple Buildings,
We need a confirmation from one of you for each building that you are now aware of this outage and on behalf of the building users you understand the impact. From your perspective the outage notification process and distribution can continue. This is the rescheduled electrical outage.
We would love to get replies as soon as possible so that we may send the official notification out quickly.
:)
Jennifer
Jennifer D. Rea
713-743-0247 office
jdrea2 at central.uh.edu<mailto:jdrea2 at central.uh.edu>
From: Simmons, Barry E
Sent: Tuesday, June 07, 2016 1:58 PM
To: Facilities Communications <faccomm at Central.UH.EDU<mailto:faccomm at Central.UH.EDU>>
Cc: Keilbach, Karl <kkeilbac at Central.UH.EDU<mailto:kkeilbac at Central.UH.EDU>>; Whitfield, Craig <cwhitfie at Central.UH.EDU<mailto:cwhitfie at Central.UH.EDU>>; Wheeler, Mike <mdwheel2 at Central.UH.EDU<mailto:mdwheel2 at Central.UH.EDU>>; dpursley at d1construction.com<mailto:dpursley at d1construction.com>; Regan, Jim <jaregan at Central.UH.EDU<mailto:jaregan at Central.UH.EDU>>; Hawkins, Terry T <tthawkin at Central.UH.EDU<mailto:tthawkin at Central.UH.EDU>>; Perlowski, Ken <krperlow at Central.UH.EDU<mailto:krperlow at Central.UH.EDU>>; Wysong, Mackenzie <mwysong at Central.UH.EDU<mailto:mwysong at Central.UH.EDU>>; Reed, Shannon <sreed2 at Central.UH.EDU<mailto:sreed2 at Central.UH.EDU>>; Benham, Mary <MBenham at Central.UH.EDU<mailto:MBenham at Central.UH.EDU>>; Johnson, Andrea L <aljohnso at Central.UH.EDU<mailto:aljohnso at Central.UH.EDU>>; Simons, Spencer <SSimons at Central.UH.EDU<mailto:SSimons at Central.UH.EDU>>; Emerson, Allen L <alemerso at Central.UH.EDU<mailto:alemerso at Central.UH.EDU>>; Gonzalez, Robert G <GRobert at Central.UH.edu<mailto:GRobert at Central.UH.edu>>; Norcom III, James G <jgnorcom at Central.UH.EDU<mailto:jgnorcom at Central.UH.EDU>>; Simmons, Barry E <besimmon at Central.UH.EDU<mailto:besimmon at Central.UH.EDU>>
Subject: RE: B825, ECFP - Fire Pump: Outage Request
Jennifer/Jacquie:
Please find attached an outage request for an electrical outage that affects a number of buildings on campus, including the construction trailer that support the Multi-disciplinary Research and Engineering Building (MREB), Building 484. Please note that this is a re-scheduling of the 06/04/2016 electrical outage request that was cancelled due to the Contractor not being prepared.
This electrical outage is required in order to maintain the MREB building occupancy schedule.
The outage request is for Saturday, June 18, 2016 beginning at 7:00AM and lasting until 5:30PM
All buildings with the exception of MREB will experience a 1 to 5 minute momentary loss of power at the beginning and end of the outage. The MREB construction trailers will be without power for the duration of the project.
I have copied the building's Building Coordinators on this request to give them a heads-ups on the request and impact to their building or project.
To mitigate the effects of the electrical outage, there will be support from the various Facility Services Shop to address issues.
Please let me know if you have any questions.
Thanks.
Barry
Sincerely,
Barry E. Simmons, PE, PMP, FMP, SFP
Sr. Project Manager
Facilities Planning and Construction
University of Houston
A Carnegie-designated Tier One public research university
713-743-9073 (Office)
832-491-6059 (Mobile)
besimmon at central.uh.edu<mailto:besimmon at central.uh.edu>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://Bug.EGR.UH.EDU/pipermail/engi-dist/attachments/20160614/20b8f7d6/attachment-0001.html
-------------- next part --------------
A non-text attachment was scrubbed...
Name: DRAFT - PLANNED ELECTRICAL OUTAGE NOTIFICATION -- FIRE PUMP PROJECT - MULTIPLE BUILDINGS (18 JUNE 2016) - UPDATED TIMES.pdf
Type: application/pdf
Size: 104495 bytes
Desc: DRAFT - PLANNED ELECTRICAL OUTAGE NOTIFICATION -- FIRE
PUMP PROJECT - MULTIPLE BUILDINGS (18 JUNE 2016) - UPDATED TIMES.pdf
Url : http://Bug.EGR.UH.EDU/pipermail/engi-dist/attachments/20160614/20b8f7d6/attachment-0001.pdf
More information about the Engi-Dist
mailing list