[CCoE Notice] Proposed Electrical Outage

Perlowski, Ken krperlow at Central.UH.EDU
Thu Apr 21 14:55:11 CDT 2016


The contractor installing the new fire pump for the Engineering and MREB buildings will need to make electrical connections to the fire pump. Below is the list of building impacts to accommodate the utility switch. The outage is necessary in order to allow the MREB building to finish on time and for the Engineering 1 and 2 fire lines to become operational.

In order to take out sub feeder 4 these building will be impacted. Let's say start time 8:00am and end time 3:00pm for an idea.

4/30/2016

8:00am

1.      Engineering 1 - 579: 5 minute complete electrical outage, emergency generator system available only.

2.      Engineering Lecture Hall 580:  5 minute complete electrical outage, emergency generator system available only.

3.      Engineering 2 - 581: 5 minute complete electrical outage, emergency generator system available only.

4.      Calhoun Lofts - 518: 5 minute complete electrical outage, emergency generator system available only.

5.      Architecture - 543:(2) 1 minute complete electrical outage, emergency generator system available only.

6.      Fine Arts - 589: (2) 1 minute complete electrical outage, emergency generator system available only.

7.      Law Library - 540: (2) 1 minute complete electrical outage, emergency generator system available only.

8.      Krost Hall - 539: (2) 1 minute complete electrical outage, emergency generator system available only.

9.      Teaching Unit 2 - 538: (2) 1 minute complete electrical outage, emergency generator system available only.

10.   Bates Law - 537: (2) 1 minute complete electrical outage, emergency generator system available only.

3:00pm - same as the morning.


11.   Engineering 1 - 579. 5 minute complete electrical outage, emergency generator system available only.

12.   Engineering Lecture Hall - 580.  5 minute complete electrical outage, emergency generator system available only.

13.   Engineering 2 - 581. 5 minute complete electrical outage, emergency generator system available only.

14.   Calhoun Lofts - 518. 5 minute complete electrical outage, emergency generator system available only.

15.   Architecture - 543. (2) 1 minute complete electrical outage, emergency generator system available only.

16.   Fine Arts - 589. (2) 1 minute complete electrical outage, emergency generator system available only.

17.   Law Library - 540. (2) 1 minute complete electrical outage, emergency generator system available only.

18.   Krost Hall - 539. (2) 1 minute complete electrical outage, emergency generator system available only.

19.   Teaching Unit 2 - 538. (2) 1 minute complete electrical outage, emergency generator system available only.

20.   Bates Law - 537. (2) 1 minute complete electrical outage, emergency generator system available only.

For anything connected to the emergency generator, there will be 2 'blips' while the power switches over.  For areas without emergency generators, power will be out.  The proposed outage will be on a Saturday to minimize problems.  Please review the timetable and let me have your comments.

Ken Perlowski
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://Bug.EGR.UH.EDU/pipermail/engi-dist/attachments/20160421/71a926d7/attachment.html 


More information about the Engi-Dist mailing list