The contractor was able to perform all of his work on the Engineering 2 water line last night.  The original water outage for Friday night and Saturday  has been canceled.

Ken Perlowski

From: Gill, Jagjeet S
Sent: Friday, May 22, 2015 11:08 AM
To: Vargas, Jacquie
Cc: Perlowski, Ken; Benham, Mary; Villarreal, Carlos; Mosley, Raymond; Hanley, Gregory A; Elizondo, Miguel A; Tajonera, Rey T; Burriello, Michael L
Subject: RE: Cullen College of Engineering 2 - Water line / valve replacement

Hi Jacquie,

We were able to connect the water mains last night at Engineering 2 and would no longer need to shut the water down again tonight and tomorrow morning (as originally planned). Please cancel the outage notification that was sent out last Friday for May 22, 2015 and May 23, 2015.

Please let me know if you have any question. Thanks,

-jack

From: Vargas, Jacquie
Sent: Friday, May 15, 2015 1:29 PM
To: Villarreal, Carlos
Cc: Wheeler, Mike; Gill, Jagjeet S; Perlowski, Ken; Benham, Mary
Subject: RE: Cullen College of Engineering 2 - Water line / valve replacement
Importance: High

Carlos:  Please review and approve the attached outage for 581 and 552 starting next week.  Both building coordinators have signed off.

Jacquie Vargas
832-842-4861

From: Gill, Jagjeet S
Sent: Thursday, May 14, 2015 1:16 PM
To: Vargas, Jacquie
Subject: FW: Cullen College of Engineering 2 - Water line / valve replacement

Jacquie,

Please see Ken's confirmation below and am still waiting for Mary Benham to approve the timings. Also, I have attached the Outage notice for you to review. Please let me know if you have any question. I would like this notice to go out duly approved by tomorrow. Thanks,


-jack

From: Perlowski, Ken
Sent: Thursday, May 14, 2015 12:23 PM
To: Gill, Jagjeet S
Subject: RE: Cullen College of Engineering 2 - Water line / valve replacement

I haven't received any feedback so let's proceed. There will be formal notice sent out, correct?

Ken Perlowski


From: Gill, Jagjeet S
Sent: Thursday, May 14, 2015 12:22 PM
To: Perlowski, Ken
Cc: Vargas, Jacquie; Villarreal, Carlos; Wheeler, Mike
Subject: RE: Cullen College of Engineering 2 - Water line / valve replacement

Hi Ken,

Please confirm if the water outage mentioned below is approved. Thanks,

-jack

From: Gill, Jagjeet S
Sent: Tuesday, May 12, 2015 1:27 PM
To: Perlowski, Ken
Cc: Vargas, Jacquie; Villarreal, Carlos; Wheeler, Mike
Subject: Cullen College of Engineering 2 - Water line / valve replacement

Ken,

As per our phone conversation yesterday about the subject, we will begin site excavation starting Monday May 18, 2015. The following schedule shut down of domestic hot and cold water is anticipated for Eng. 2 (bldg. 581) only.

Engineering 1 (bldg.. 579) and Engineering lecture hall (bldg.. 580) will not be affected by this outage.

Thursday May 21, 2015 from  5PM - 9PM
Friday       May 22, 2015 from  5PM - 9PM
Saturday May 23, 2015 from  9AM - 1PM

Please let us know if this works for you or if we need to make some adjustments.
Thanks,

-jack

Jagjeet S Gill, FMP SFP
Sr. Construction Project Manager
Facilities Management
University of Houston
A Carnegie-Designated Tier One Public Research University
713/743-1505
jsgill at central.uh.edu<mailto:jsgill at central.uh.edu>

-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://Bug.EGR.UH.EDU/pipermail/engi-dist/attachments/20150522/adae1495/attachment.html 


More information about the Engi-Dist mailing list